To consider the report of the Director of Strategy, Performance and Governance (copy enclosed, Members’ Update to be circulated)*.
Minutes:
|
Application Number |
FUL/MAL/18/01264 |
|
Location |
Madison Heights, Park Drive, Maldon, Essex, CM9 5JQ |
|
Proposal |
Two single storey extensions to the front elevation and retrospective permission for the erection of a canopy replacing the two former balconies |
|
Applicant |
Michael Kirkham |
|
Target Decision Date |
13.02.2019 |
|
Case Officer |
Nicola Ward |
|
Parish |
MALDON EAST |
|
Reason for Referral to the Committee / Council |
Council Owned Land |
Members were advised that contrary to the first page of the Officers report there were suggested conditions (detailed at the end of the report) to which this application would be subject if Members were mindful to approve it.
RESOLVED that this application be APPROVED subject to the following conditions:
The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
1 The development hereby permitted shall accord with that shown on drawing numbers 568-01, 568-02, 568-03, 568-04, 568-05, 568-06, 568-07 and 568-08
2 The external surfaces of the development hereby approved shall be constructed of materials and finish as detailed within the application.
No development shall commence, other than where necessary to carry out additional investigation, until a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment has been submitted to and approved in writing by the local planning authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures.
The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. The development hereby permitted shall not commence until the measures set out in the approved scheme have been implemented, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority may give approval for the commencement of development prior to the completion of the remedial
3 measures when it is deemed necessary to do so in order to complete the agreed remediation scheme. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works.
This shall be conducted in accordance with the Essex Contaminated Land Consortium's 'Land Affected by Contamination: Technical Guidance for Applicants and Developers' and DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11'. The development hereby permitted shall not commence until the measures set out in the approved report have been implemented.
4 The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works.
Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced and submitted to the Local Planning Authority for approval.
The written verification shall include that:
(i) All contaminated material removed from the site is removed by an appropriate licensed contractor to a facility approved by the Environment Agency.
(ii) All imported material is suitable for its intended use.
(iii) All agreed remediation measures identified as necessary in the contaminated land assessment have been undertaken to render the site suitable for the use specified.
This must be conducted by a competent person and in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11' and the Essex Contaminated Land Consortium's ‘Technical Guidance for Applicants and Developers' and is subject to the approval in writing of the Local Planning Authority.
5 All loading / unloading / reception and storage of building materials and the manoeuvring of all vehicles, including construction traffic shall be undertaken within the application site, clear of the public highway.
Supporting documents: