Minutes:
|
Application Number |
out/mal/17/00171 |
|
Location |
Land Adjacent to The Poplars Plains Road Little Totham |
|
Proposal |
Erection of Detached Dwelling in lieu of authorised Scrap Yard and Licensed Scrap Metal Business |
|
Applicant |
Mr & Mrs Wakeling |
|
Agent |
Stanfords |
|
Target Decision Date |
12 April 2017 |
|
Case Officer |
Terry Hardwick, TEL: 01621 876220 |
|
Parish |
LITTLE TOTHAM |
|
Reason for Referral to the Committee / Council |
Departure from the Local Plan 2005 |
Following the Officer’s presentation of the report, a question was raised about a whether a condition should be added to include removal of business buildings prior to a residential dwelling being built. It was agreed by the committee to approve the application in line with the Officer’s recommendation with the added condition of prior removal of business buildings.
RESOLVED that this application be APPROVED subject to the following conditions:
1. The development shall be carried out in accordance with plans and particulars relating to the layout, scale, appearance, the means of access to the site and the landscaping of the site (hereinafter called "the reserved matters"), for which approval shall be obtained from the local planning authority in writing before any development is begun. The development shall be carried out fully in accordance with the details as approved.
2. Application for the approval of the reserved matters shall be made to the local planning authority before the expiration of three years from the date of this permission.
3. The development hereby permitted shall be begun within two years from the date of the final approval of the reserved matters. The development shall be carried out as approved.
4. As part of the Reserved Matters written details or samples of all materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the local planning authority. The development shall be carried out using the materials and details as approved.
5. As part of the Reserved Matters details of the siting, height, design and materials of the treatment of all boundaries including gates, fences, walls, railings and piers have been submitted to and approved in writing by the local planning authority. The boundary treatment as approved shall be constructed prior to the first use/occupation of the development to which it relates and be retained as such thereafter.
6. As part of the Reserved Matters full details of both hard and soft landscape works to be carried out have been submitted to and approved in writing by the local planning authority. These details shall include the layout of the hard landscaped areas with the materials and finishes to be used and details of the soft landscape works including schedules of shrubs and trees to be planted, noting the species, stock size, proposed numbers/densities and details of the planting scheme’s implementation, aftercare and maintenance programme. The hard landscape works shall be carried out as approved prior to the beneficial occupation of the development hereby approved unless otherwise first agreed in writing by the local planning authority. The soft landscape works shall be carried out as approved within the first available planting season (October to March inclusive) following the commencement of the development, unless otherwise first agreed in writing by the local planning authority. If within a period of five years from the date of the planting of any tree or plant, or any tree or plant planted in its replacement, is removed, uprooted, destroyed, dies, or becomes, in the opinion of the local planning authority, seriously damaged or defective, another tree or plant of the same species and size as that originally planted shall be planted in the same place, unless the local planning authority gives its written consent to any variation.
7. Prior to first occupation of the proposed development, the proposed vehicular access shall be constructed at right angles to the highway boundary and to a width of 3.7 metres and shall be provided with an appropriate dropped kerb vehicular crossing of the footway/highway verge to the specifications of the Highway Authority.
8. Prior to the occupation of the development the parking areas shall be constructed, surfaced, laid out and made available for such purposes in accordance with the approved scheme and retained as such thereafter.
9. Prior to commencement of the proposed development, a vehicular turning facility for motor cars of a design which shall be approved in writing by the Local Planning Authority, shall be provided within the site and shall be maintained free from obstruction in perpetuity.
10. No unbound material shall be used in the surface finish of the driveway within a distance of 6.0m from the highway boundary of the site.
11. Any gates that may be erected at the vehicular access shall be inward-opening into the site only and shall be recessed a minimum of 6m from the highway boundary
12. Notwithstanding the details submitted with this application, no development shall commence, other than that required to carry out additional necessary investigation which in this case includes demolition, site clearance, removal of underground tanks and old structures, and any construction until an investigation and risk assessment has been submitted to and approved in writing by the local planning authority. The risk assessment shall assess the nature and extent of any contamination on the site whether or not it originates on the site.
The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The report of the findings must include:
(i) a survey of extent, scale and nature of contamination;
(ii) an assessment of the potential risks to:
· human health,
· properly (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes,
· adjoining land,
· groundwaters and surface waters
· ecological systems
· archaeological sites and ancient monuments;
(iii) an appraisal of remedial options, and proposal of the preferred option(s).
This must be conducted by a competent person and in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11' and the Essex Contaminated Land Consortium's 'Technical Guidance for Applicants and Developers' and is subject to the approval in writing of the Local Planning Authority.
13. No development shall commence, other than where necessary to carry out additional investigation, until a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment has been submitted to and approved in writing by the local planning authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. The development hereby permitted shall not commence until the measures set out in the approved scheme have been implemented, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority may give approval for the commencement of development prior to the completion of the remedial measures when it is deemed necessary to do so in order to complete the agreed remediation scheme. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works.
This must be conducted by a competent person and in accordance with DEFRA and t Agency's 'Model Procedures for the Management of Land Contamination, CLR 11' and the Essex Contaminated Land Consortium's 'Technical Guidance for Applicants and Developers' and is subject to the approval in writing of the Local Planning Authority.
14. The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development, other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced. This must be conducted by a competent person and in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR11' and the Essex Contaminated Land Consortium's 'Technical Guidance for Applicants and Developers' and is subject to the approval in writing of the Local Planning Authority.
15. Prior to the commencement of the development, a sustainable surface water urban drainage scheme (SuDS) to serve the development shall be submitted to and agreed in writing by the local planning authority. The agreed scheme shall be implemented prior to the first occupation of the development. The applicant shall demonstrate that the surface water scheme will ensure that as a minimum:
· Run-off from the site is limited to greenfield rates for a storm event that has a 100% chance of occurring each year (1 in 1 year event). The development should be able to attenuate (manage water on site) for 1 in 100 year events plus 40% climate change allowance;
· If the land is designated as a Brownfield Site it should aim to limit run-off for a storm event that has a 100% chance of occurring each year (1 in 1 year event) OR demonstrate 50% betterment of the current rates.
16. Prior to the commencement of the development, details of the foul drainage scheme to serve the development shall be submitted to and agreed in writing by the local planning authority. The agreed scheme shall be implemented prior to the first occupation of the development.
17. The construction of the new dwelling hereby permitted shall not commence unless and until the existing structures on the site has been demolished and the resulting material removed from the site.